RailNET In a NEMA Enclosure Installation Manual
RailNET In a NEMA Enclosure allows for easy installation by using mindful packing techniques.
Site Considerations
Pre-construction
- Find the transducer location first. This is the center of the site. The center of the transducer must be located between two ties. This allows the cable at the bottom of the transducer to enter the Carflex conduit without binding.
- Find the tower locations. Since the center of the antennas and the center of the transducer must line up, the towers will be offset from the transducer. (The antennas mount to the side of the tower.)
Areas to Avoid
Comet Electronics recommends that the following site areas are avoided. Use this list as a guide only. Since all installations are unique in some manner, avoiding these areas is not always possible. A survey of each site should be done to determine preferred equipment locations, conduit runs, and antenna configuration based upon the particular application. The user and the system integrator must ensure correct and accurate system operation in the event the areas described below cannot be avoided.
- Large metallic objects and obstructions in close proximity to the reading area
- Areas where reverse train movements occur
- Areas where train switching moves occur
- Areas where “building” moves occur (dropping and adding cars)
- Areas where train stoppage in front of reader systems is likely to occur
- Areas with severe or multiple curves in the track
- Switches
- Track joints
Foundation
Install house foundation legs at top of tie level. All trenching is to be 36" below top of tie. Set tower foundations. Recommended: 200lbs of Sakrete for the nearside.
Conduit
Install all conduits in the same trench. Lay conduit out, make the necessary cuts, glue cut pieces together as necessary, and bury the conduit.
Conduit runs on drawings are guidelines. They may be changed to fit site specific requirements. Use sweeps, not elbows!
Towers
Install tower sections and tower caps. There are holes present at the bottom of the tower. Use these holes to guide drilling through the foundation, and secure tower to foundation using provided bolts. Secure towers with six bolts each, for twelve total bolts.
Ground Rods
Install ground rods and cabling. (Pigtail at corner ground rods into hut.)
Junction Box and AEI Box
Nearside: AEI Box
Farside: Junction Box
Heliax
Antennas
Wiring Power to the AEI Box
Power must be wired into the AEI box by a licensed electrician.
Wheel Sensor
Refer to Frauscher Wheel Detector Installation and Optimization for instruction on installing the wheel sensor.
Presence Subsystem
Install loop cable on track. Loop cable must be twisted 5 times per foot from track to pedestal (if used) or junction box. Install twisted loop cable in Carflex conduit.