*Site should be readily accessible to nearby roads to facilitate maintenance. | *Site should be readily accessible to nearby roads to facilitate maintenance. | ||
*Site should be located near commercial power source. | *Site should be located near commercial power source '''(NOT necessary for solar installations)'''. | ||
*Site should be located with consideration to the availability of appropriate communication facilities for system reporting and maintenance (cell coverage). | *Site should be located with consideration to the availability of appropriate communication facilities for system reporting and maintenance (cell coverage). | ||
*Site should be located to avoid discontinuities in the track structure (joints, switches, grade or rail crossings) in the immediate vicinity of the | *Site should be located to avoid discontinuities in the track structure (joints, switches, grade or rail crossings) in the immediate vicinity of the SensorLink system. | ||
*Site should provide sufficient space to install wayside equipment with respect to railroad clearance restriction requirements. | *Site should provide sufficient space to install wayside equipment with respect to railroad clearance restriction requirements. | ||
*The site should be located in order to satisfy railroad application requirements and with a consideration of the communication and processing lead-time required by the user of the | *The site should be located in order to satisfy railroad application requirements and with a consideration of the communication and processing lead-time required by the user of the data.<br> | ||
*High vandalism areas should be avoided. | *High vandalism areas should be avoided. | ||
*Avoid low areas where flooding may occur. | *Avoid low areas where flooding may occur.<br> | ||
*Site selections should be made with an understanding of the railroad traffic patterns. | |||
*Site selections should be made with an understanding of the railroad traffic patterns | |||
*If feasible, sites should be located to avoid potential sources of interference including large metallic objects and obstructions in close proximity to the reading area, reflective surfaces, and high voltage power lines, and other fixed and portable AEI reader systems. | *If feasible, sites should be located to avoid potential sources of interference including large metallic objects and obstructions in close proximity to the reading area, reflective surfaces, and high voltage power lines, and other fixed and portable AEI reader systems. | ||
*In order to reduce the potential for interference and subsequent performance degradation, site selection should be made to avoid having two AEI systems powered on at the same frequency at the same time. Two like frequencies should be kept a minimum of 1,500 Ft. apart. AEI transmitter frequencies are: 902.25 MHz, 903.75 MHz, 910.00 MHz, '''911.50 MHz''', 913.00 MHz, 915.00 MHz, 917.00 MHz, 918.50 MHz, 920.00 MHz, and 921.25 MHz<br> | *<span style="background-color: rgb(241, 196, 15);" >In order to reduce the potential for interference and subsequent performance degradation, site selection should be made to avoid having two AEI systems powered on at the same frequency at the same time. Two like frequencies should be kept a minimum of 1,500 Ft. apart. AEI transmitter frequencies are: 902.25 MHz, 903.75 MHz, 910.00 MHz, '''911.50 MHz''', 913.00 MHz, 915.00 MHz, 917.00 MHz, 918.50 MHz, 920.00 MHz, and 921.25 MHz</span><br> | ||
= Pre-construction = | = Pre-construction = | ||
Revision as of 13:16, 2 June 2025
Introduction
Welcome to the installation guide for your new SensorLink system. This article provides instructions to ensure a safe and efficient installation. Safety is paramount throughout this process. Railroad environments present unique hazards, and strict adherence to all safety protocols is mandatory. Precise workmanship is equally critical for the reliable operation of this SensorLink system. Carefully follow each step, double-check connections, and ensure all components are securely mounted. Your diligence in both safety and workmanship will guarantee a successful and long-lasting installation.
Read Instructions Thoroughly Before Beginning; Understanding all of the Steps will Help Avoid Difficult Situations
Scope of Supply
The installation package includes all necessary components for the complete installation of your SensorLink system.

Provided Components:
- NEMA Enclosure, which houses the SensorLink System
- SensorLink Processor
- MPRX
- Surge Suppression
- Cellular Modem
- Battery Charger
- Sodium Ion Battery
- Cellular Antenna (mounted on top of enclosure)
- Two 4" x 4", 10-foot Galvanized Metal Posts
- Cables, Conduit and Fittings for system connections
- Two RFID Antennas
- Frauscher Wheel detector and accessories
- Radar Presence kit
Tools and Materials Needed
Installation also requires:
- Basic hand tools
- Drill driver with Phillips and star bits
- Pickaxe
- Two-person auger, with a bit that is 8" in diameter and 36" long
- 250 lbs dry concrete
- 5 gallons of water
- Two magnetic levels
- Block-and-tackle rig (recommended)
Process Overview
The following is a general installation process overview for a SensorLink system, broken down into key stages:
- Site Preparation and Planning:
- Site Survey: Conduct a thorough site survey to determine optimal reader and antenna placement. Identify potential obstructions and assess cabling pathways. If the site is to be served by an electrical circuit, check for access to power.
- Permitting and Approvals: Obtain all necessary permits and approvals from relevant authorities.
- Safety Planning: Develop a detailed safety plan, including emergency response procedures, as sites are often remote.
- Material Acquisition: Gather all required materials.
- Post and Ground Rod Installation
- SensorLink Subsystems
- Electrical InstallationXXX
- System Configuration and Commissioning (Optimization)
- Power-Up and Initial Checks: Power on the system and perform initial checks to verify proper operation.
- Tag Testing: Perform tag testing to verify accurate tag reads and system performance.
- Data Verification: Verify that the system is transmitting data correctly to the designated data collection system.
- Power-Up and Initial Checks: Power on the system and perform initial checks to verify proper operation.
- Final Inspection and Documentation:
- Final Inspection: Conduct a thorough final inspection to ensure all components are properly installed and functioning.
- Documentation: Complete all necessary documentation and optimization checklist.
Site Considerations
- Site should be readily accessible to nearby roads to facilitate maintenance.
- Site should be located near commercial power source (NOT necessary for solar installations).
- Site should be located with consideration to the availability of appropriate communication facilities for system reporting and maintenance (cell coverage).
- Site should be located to avoid discontinuities in the track structure (joints, switches, grade or rail crossings) in the immediate vicinity of the SensorLink system.
- Site should provide sufficient space to install wayside equipment with respect to railroad clearance restriction requirements.
- The site should be located in order to satisfy railroad application requirements and with a consideration of the communication and processing lead-time required by the user of the data.
- High vandalism areas should be avoided.
- Avoid low areas where flooding may occur.
- Site selections should be made with an understanding of the railroad traffic patterns.
- If feasible, sites should be located to avoid potential sources of interference including large metallic objects and obstructions in close proximity to the reading area, reflective surfaces, and high voltage power lines, and other fixed and portable AEI reader systems.
- In order to reduce the potential for interference and subsequent performance degradation, site selection should be made to avoid having two AEI systems powered on at the same frequency at the same time. Two like frequencies should be kept a minimum of 1,500 Ft. apart. AEI transmitter frequencies are: 902.25 MHz, 903.75 MHz, 910.00 MHz, 911.50 MHz, 913.00 MHz, 915.00 MHz, 917.00 MHz, 918.50 MHz, 920.00 MHz, and 921.25 MHz
Pre-construction
- Determine the transducer location first. This is the center of the site. The center of the transducer must be located between two ties. This allows for the transducer claw to clamp under the rail.
- Mark the 4" x 4" post locations. Posts should be directly out from the transducer -- 12 feet, 6 inches from center of track.
Before digging, contact a qualified utility locator service. Utilities need to be marked before digging to safely avoid them. See below a non-comprehensive list of utility locator services. Local authorities need to be notified before work begins.
| Service Provider | Locality | Contact |
| Call 811 | United States | Call 811 or visit https://call811.com/ |
| Click Before You Dig | Canada | Visit https://www.clickbeforeyoudig.com/ |
Comet Industries is not affiliated with or endorsed by any of the service providers listed.
Earthwork
Two 4" x 4" galvanized posts and the 1" Sealtight conduit (with the far-side antenna cable inside) need to be installed below grade.

Post holes
- Holes should be located 12 feet, six inches from the center of track.
- Holes should be aligned with wheel sensor (transducer)
- Holes must be 8 inches in diameter and 3 feet deep.
Shallow Trench
- One 3"-deep conduit channel is needed between the two post holes.
- Use the pickaxe to dig out a small trench from the base of the far-side antenna, under the track, and out the other side to connect with the Enclosure

SITE LAYOUT DIAGRAM
SITE ELEVATION DIAGRAM
Posts
4x4 galvanized posts 400072 with post caps 400079 will be installed on each side of the track.
Posts should be setback per layout, 12 foot 6 inches from center of track. They should be angled parallel with track. Both posts should be set in 100lbs of sack concrete and covered in native backfill. In most cases, adding dry concrete is sufficient. No need to cure before completing installation. Posts are to be hand backfilled and tamped, checking and adjusting for plumb, square, and level.
- Install post cap on one end of the post prior to erecting the post. A cap should be installed on both posts.
- Set the post in ballast, capped end upright.
- Mark on the posts 42.5" from top of rail. This marks where the RF antennas will be placed later.
Ground Rods
Drive the ground rods 400421 directly after back-fill before further assembly to help keep a clear workspace. If you mushroom the head of the rod during installation, it will need to be ground back to profile in order to CADweld the bonding wire to it. NEED PLACEMENT DIAGRAM
- Drive one ground rod 2-6" from each post.
- Ground Rods should be driven to 4-8" above grade.
Subsystem Install
Solar Panel

When attaching the solar panel, be aware of its position relative to the sun. In the northern hemisphere, south facing solar panels allow for optimal exposure to the sun. Depending on positioning of the rail, optimal placement may not be possible.
- Assemble brackets onto solar panel.
- Attach to nearside post using provided U-bolts according to optimal placement.
Radar Presence Detector
The radar must be attached to the nearside post, facing the rail. PHOTO NEEDED, MORE PRODUCT INFO NEEDED
- Attach radar facing the track, using provided U-bolts, to nearside post.
SensorLink Enclosure
The system is ready for the mounting of the SensorLink Enclosure [INSERT PART NUMBER].
| The SensorLink enclosure is heavy and awkward to handle. Plan your movements, this is a multiple person job. |
|---|
Before attaching the enclosure, mark on the nearside post where the enclosure will be attached. Ideal placement of the SensorLink enclosure will ensure accessibility when working inside the enclosure later. The SensorLink enclosure should be attached on the side of the post that is opposite to the track.
[INSERT ORIENTATION DIAGRAM]
- Attach to nearside post using provided U-Bolts on the side of the post opposite to the track.
Antenna Mounting

NEED DIAGRAMS
Two ParaPanel Antennas 400942 need to be installed, one on each post. The vertical center of the antenna should be 42 inches above top of rail, facing the track. If the posts were marked during Posts, the mark can be used to aid in mounting the antennas at the proper height.
Note: Mounting hardware for the parapanel antenna is stainless steel. Caution should be taken to avoid thread galling. This includes thread lubrication (best case "anti-seize"), and careful handling.
- Attach L-brackets to the back of the antennas using provided screws.
- Mount the nearside antenna first. The antenna should be attached facing the track, opposite the SensorLink enclosure.
- The provided plate sits against the long side of the L-bracket.
- The U-bolts attach around the tower post.
- Attach the second antenna directly across from the first in the same manner.
Antenna Connections
Sealtight conduit 400514 is used to connect the RF antennas to the SensorLink enclosure. Sealtight conduit is provided in the kit for this purpose.
The conduit should be laid in the 3" deep channel made in Earthwork.
Wheel Sensor

Refer to Frauscher Wheel Detector Installation and Optimization for instruction on installing the wheel sensor to the rail. The mounting point on the track should be in line with the antennas as much as possible.
- Cut the Frauscher's protective hose to the appropriate length and install using the grey cable fitting on the bottom of the enclosure.
- Cut the sensor wire to length, (with a service loop) and landed in the enclosure as shown. NEED PHOTO/DIAGRAM
Presence Detector Connections
Materials Needed
Tools Needed
Electrical Connections
Grounding Connections
Materials Needed
- No. 6 Bare Copper Wire
Tools Needed
- Wire cutter
Procedure
- On the nearside post, partially unscrew the grounding lug's inner bolt and insert copper wire. Secure wire by tightening the inner bolt.
- Secure wire to grounding rod with grounding rod clamp.
- Cut the copper wire on the excess side of the grounding rod.
- On the farside, screw ground lug to antenna.
- Repeat steps 1-3 on the farside post.
Solar Panel Connections

Connections from the solar panel should be run to the enclosure. The cables should run through the second and third black cable fittings. The cable fittings are found on the bottom of the enclosure.
Batteries
An area inside the SensorLink enclosure has been marked for battery 400266 placement.
- Install the battery in the marked area.
- Connect the battery using the color codes (Black -)(Red +)
Final Inspection
Calibrating the wheel sensor, checking the reader and reporting to RSM. NEEDS MORE INFORMATION